Post Time:Aug 05,2009Classify:Industry NewsView:469
Workers with CBO Glass began installing glass panels Monday to enclose the atrium of the Carousel Center mall expansion in Syracuse. It will take two weeks to install 150 glass panels and another two weeks to frame them.
Construction on the first phase of the Destiny USA project was halted in June when Citigroup stopped advancing money on a $155 million loan.
A spokesperson for the developer said their priority is making sure the building is safe and weather-tight while the loan dispute is pending in court.
Workers with CBO Glass install glass panels Monday to begin enclosing the atrium of the Carousel Center mall addition in Syracuse.
Source: syracuseAuthor: shangyi